Brigade Autograph project cost and escrow account details show the cost of the township and where buyer payments are held. The total project cost is ₹3,673.44 Crore. Land accounts for ₹670.88 Crore and development for ₹3,002.55 Crore, as certified by a chartered accountant in Form 1. Buyer payments go into RERA escrow accounts at Kotak Mahindra Bank, Lavelle Road, Bengaluru.
Brigade Autograph Total Project Cost
The total project cost of Brigade Autograph is ₹3,673.44 Crore. The figure is declared in the Karnataka RERA registration for Floris & Commercial at Brigade Autograph.
| Cost Head | Amount |
|---|---|
| Cost of land (C1) | ₹670.88 Crore |
| Cost of layout development (C2) | ₹3,002.55 Crore |
| Total project cost (C1 + C2) | ₹3,673.44 Crore |
Land makes up 18% of the cost, and development makes up 82%.
Estimated Construction Cost Breakdown
The estimated construction cost of Brigade Autograph is ₹2,884.66 Crore. The project engineer signed the cost sheet on 4 November 2026, and it splits the build into seven packages.
| Package | Amount |
|---|---|
| Civil and landscape, including entrance portal, clubhouse, roads, footpaths and painting | ₹1,983.67 Crore |
| Electrical package | ₹162.48 Crore |
| Plumbing package | ₹112.50 Crore |
| Overhead tanks, pump room, underground sump, STP and organic waste converter | ₹65.00 Crore |
| Signage and CCTV lighting | ₹8.29 Crore |
| Taxes | ₹419.73 Crore |
| Administrative costs | ₹132.99 Crore |
| Total | ₹2,884.66 Crore |
Civil and landscape work is 69% of the construction estimate.
The Brigade Autograph Escrow Account
The Brigade Autograph escrow account is the bank set-up that holds buyer payments under RERA rules. It has three linked accounts at Kotak Mahindra Bank, Lavelle Road branch.
- 100% collection account: receives every payment made by buyers.
- 70% RERA account: receives 70% of the collections, used only for land and construction costs of this project.
- 30% account: receives the remaining 30% for the promoter's other expenses.
Withdrawals from the 70% account follow construction progress. Each needs certificates from the engineer, the architect and a chartered accountant.
How the Escrow Protects Buyers
The escrow protects buyers by keeping most of their money tied to this project. Funds collected for Brigade Autograph cannot move freely to other projects.
- Ring-fenced funds: 70% of buyer payments stay with the project for land and construction.
- Progress-linked withdrawals: money comes out of the RERA account in step with work on site.
- Audit trail: the accounts are audited and reported to Karnataka RERA.
Payments and the Escrow Account
Payments for a Brigade Autograph home go to the collection account named in the allotment letter. Buyers check that the account is in the project name. Each receipt mentions the unit number.
Frequently Asked Questions
1. What is the total project cost of Brigade Autograph?
The total project cost is ₹3,673.44 Crore, with ₹670.88 Crore for land and ₹3,002.55 Crore for development.
2. Which bank holds the Brigade Autograph escrow account?
The escrow accounts are with Kotak Mahindra Bank, Lavelle Road branch, Bengaluru.
3. What are the 100%, 70% and 30% accounts?
All buyer payments enter the 100% account. 70% then moves to the RERA account, and 30% to the promoter's account.
4. How much will construction of Brigade Autograph cost?
The engineer's cost sheet puts construction at ₹2,884.66 Crore, including ₹1,983.67 Crore for civil and landscape work.
5. How much is set aside for water and waste systems?
₹65 Crore is set aside for overhead tanks, the pump room, the underground sump, the STP and the organic waste converter.
6. Who certified the project cost?
The land and development costs are certified by a chartered accountant in Form 1, and the construction estimate is signed by the project engineer.